5. VICTORIAN POWER STATIONS
5.1 Privatisation of power generation in Victoria.
Privatisation in Victoria has not been a single simple activity but has taken 10 years, and in some ways it still continues. There were three major approaches to privatisation in Victoria.
5.2 Improvement in availability in Victoria
The historical availability figures for Victorian power stations from
the period of government ownership prior to any privatisation are given
in the SECV 1990/1 Annual report (SECV 1991). More recent data for
the individual power stations is available from company newsletters.
This data is compared on Table 6.
| Power station | 1989 – 91(3 year average) | Recent |
| Loy Yang (A) | 85.0% CF | 96.4 (1st half 99) |
| Yallourn (W) | 69.7 | 91.6 (98/99)* |
| Hazelwood | 56.7 | 89.4 (7 months 99) |
Prior to privatisation, the capacity factor (CF) for the large coal burning power stations were very close to the AF because of the way the system was run. These stations were considered to be “high on the order of merit” and difficult to start up and were generally loaded as soon as they were available.
Loy Yang A. between 1989 and 1991 averaged an AF of 85%. In 1998 Loy Yang A achieved an AF of 97.4% (Loy Yang 1997). This is actually close to the absolute possible value of the station (see Table 5) and was aided by a there being no large planned outage in that year. The average which Loy Yang can achieve is about 95%. Even so this change is significant and it is like adding another 200 MW to the station.
Hazelwood, between 1989 and 1991 averaged AF of 56.7% which is a very poor figure. Hazelwood had suffered persistent long term problems with reliability and in fact 1989-91were actually better than previous years. For most of its life the station struggled with AFs between 48% and 60% (SECV 1991). There had been only two occasions, in 1974 and 1991, lasting only a few weeks on each occasion, when all 8 boilers had been simultaneously in operation.
In 1998 (to November) an AF of 82.7% was achieved (Hazelwood 1998). This change is, on its own, like having a new power station of over 400 MW on the grid.
When events immediately prior to privatisation are considered, the Hazelwood case is particularly dramatic. In 1996 only 6 of the 8 boilers were in service. Unit 7 had been severely damaged by a severe thermal transient in 1993 and Unit 8, which shares some common equipment with Unit 7, was in mothballs. Moreover the state owned corporation at this time considered Hazelwood to be low on its order of generation merit order so generally only 3 or 4 of the remaining 6 units were regularly in service.
The prior poor performance of Hazelwood was not because of neglect.
While it belonged to the SECV, Hazelwood received enormous attention and
expenditure but achieved very little in terms of improved output.
Nowadays Hazelwood is a successful station for its age.
5.3 The causes of improvement
The cause of this change of fortune for Hazelwood and the solid improvement in the other stations is one of the most interesting issues in electricity generation in Australia. The fundamental reasons seem to be better management of maintenance and operations.
There are two basic ways that AF improves:
Other issues were discussed:
The surveying, which would be required to identify what the phrase "change of culture" encompasses, has not been conducted among the workers to the author's knowledge. It is to be noted that the companies which now operate and maintain the power generation system are, in many cases, largely composed of former SECV employees.
One issue, which has been pointed out to the author by a number of people, is that many of the improvements in performance were made during the period of corporatisation and outsourcing and before the asset sales. Thus it is not clear that the actual equity arrangements of a plant are critical for performance issues
5.4 Adequacy of generation capacity for the future
One of the significant issues in electricity privatisation is whether
there will be adequate generation capacity in the future. The problem
surrounds the peak load in the state. Victoria is a summer peaking
state: the largest demand occurs on a few hot days in summer.
As shown on Figure 2 projections by NEMMCO indicate that current capacity
will be inadequate on hot days by about 2001- 2004.
Any new capacity will be gas fired. Because this new plant may only be used for a few days a year, the cheapest capital option would have to be used. There has already been suggestions in the press that open ended gas turbine will be built on the Edison Mission site in the LaTrobe Valley. Even so it is likely that this extra capacity will have to be financially encouraged by the State of Victoria (through the Office of the Regulator General). This is required since it is unlikely to be commercially attractive to build a power station, which would only operate for a few hours a year. The author is unaware of any public information as to how this encouragement is being arranged.
In the NEMMCO data on Fig 2, demand for the peak is assumed to increase
at about 170 MW per year and there is inadequate reserve capacity by 2004/5.
VPX however in 1998 recorded faster growth rates. "The strong growth in
the Victorian economy, high growth in air-conditioning load and higher
than average temperatures during summer have produced the forecast 4.7%
per annum demand growth rate which represents about 350 MW per year." (VPX
1998). If the growth which occurred in 1996/7 were to be continued,
then additional generation capacity will be required earlier than shown
on Fig 2, perhaps as early as 2001.
5.5 Value of electricity sales from Victoria to the other states
Electricity now represents a significant export industry for Victoria. Data can be obtained from the NEMMCO web site under the heading Regional Summary Reports.
A brief survey of this data, which is presented weekly, suggests that
there is typically about $1.5 million of electricity being sold to South
Australia each week. The trade to NSW varies considerably and is
confused by the fact that the Snowy Scheme also participates in the market
as a separate entity. However a typical figure of the trade North
may be $0.5 million per week. If that data is averaged over the entire
year the trade had a net worth of about $80-$100 m to Victoria.
National Conference 1999
Home